SALEM, S.D. (KELO.com) – The South Dakota Department of Transportation (SDDOT) says work is underway to reconstruct Interstate 90 westbound lanes from Salem to Humboldt.
Two-way traffic will be used in the eastbound lanes during the reconstruction of the westbound lanes, which began this week. Two-way traffic will continue until the reconstruction of the westbound lanes are completed in mid-November.
Work on the project includes recycling the existing surfacing, placement of 11 ½ inches of new concrete surfacing with asphalt shoulders, reconstruction of two bridges, rehabilitation of two additional bridges, replacement of culverts, and regrading of low-lying areas.
Westbound on and off-ramps at exit 368 (Canistota) will be closed for the duration of the reconstruction.
Westbound on and off-ramps at exit 364 (U.S. Highway 81, Salem) and exit 374 (Montrose) are currently closed until asphalt surfacing is complete. Asphalt surfacing is currently being scheduled for late April when hot mix asphalt is available.
Eastbound ramps will not be affected during the project.
The prime contractor on this $37.5 million project is Michels Road & Stone, Inc. of Brownsville, WI.
The roadway reconstruction is scheduled to be completed and reopened by Nov. 18, 2022, with final lane striping to be completed in 2023.
(The SDDOT contributed this report/news release.)