SIOUX FALLS, S.D. (KELO.com) — The big pour started today on the 26th Street and Southeastern Bridge project.
City engineers say they will pour 1,000 cubic feet of cement today.
That is 100 cement trucks.
Then, the concrete will need about seven days to cure.
They say they’ll be moving traffic to the south side of the bridge the first or second week of June.
See the City’s video on Twitter here.